SCHOOL CONSTRUCTION CHANGE ORDER LIMITATIONRESOLUTION NO.
458
WHEREAS, the Everett School District No.2 is presently engaged in anumber of construction projects and anticipates such activity will continue on asubstantial basis in the future; andWHEREAS, the need arises from time to time on such construction projectsfor consideration of change order requests; andWHEREAS, the Board of Directors of the Everett School District No.2determines it to be in the best interest of the School District to delegate reviewand approval authority on a limited basis for certain change orders; thus,BE IT RESOLVED, that the Board of Directors of Everett School District...